Construction of Tourist Boat Shelter in Anafi

The construction of the marina that is located on the South Coast of the Island of Anafi and specifically northeast of the Port of Agios Nikolaos has already started.

The operations are held at the northwest of the coastal quays, before the landscaped coastal front as well as along the coastal road of Ormos settlement at Agios Nikolaos.

More specifically, the project includes the following milestones:

  • Construction of a C level pier, 116.05m long and 5.00m wide.
  • Construction of new coastal quays, to the west of the platform, 116m long and more than 5.00 m wide, as well as dredging of a canal and a basin at -4.00m from MST.
  • Landscaping which involves the construction of land floors, configuration of architecture and complete installation of marine service network.
  • Installation of permanent anchorages.
  • Construction of a service building shelter of the 80m² and installation of navigation lights.